GovWire

Guidance: Operating peaking combustion power plant in an emergency in winter 2022: RPS 268

Environment Agency

October 27
13:23 2022

Details

This regulatory position statement (RPS) does not change your legal requirement to comply with your environmental permit.

However, if you comply with the requirements of this RPS the Environment Agency will not normally take enforcement action if you exceed the annual operating hour limits in your Industrial Emissions Directive (IED) permit because you need to operate at times of electricity shortage in 2022.

This enforcement position does not apply to any other legal requirements.

Published 27 October 2022

Recent Comments

Follow Us on Twitter

Share This


Enjoyed this? Why not share it with others if you've found it useful by using one of the tools below: