Competition Markets Authority
March 9
12:18
2023
Timetable for applications for permission
Date | Action |
2 March 2023 | Application for permission to appeal submitted by NPg |
16 March 2023 | Deadline for Ofgem to make any representations or observations in relation to the application for permission to appeal |
22 March 2023 | If Ofgem does not make any representations or observations, deadline for the CMA to make its decision on whether to grant permission to appeal |
30 March 2023 | If Ofgem makes any representations or observations on 16 March 2023, deadline for the CMA to make its decision on whether to grant permission to appeal, (this deadline is 10 working days starting with the first working day after receipt of Ofgems representations or observations). |
Notice of appeal
2 March 2023: Northern Powergrid (Northeast) Plc and Northern Powergrid (Yorkshire) Plc have applied for permission to appeal GEMAs decision of 3 February 2023 on the proposed modifications to their electricity distribution licences. These licence modifications are based on GEMAs RIIO-ED2 price control Final Determinations of 30 November 2022.
- (9.3.23)
Contact
Any queries or submissions relating to this matter should be sent to: ED2Appeal@cma.gov.uk