Administrative timetable
Published on 22 April 2021, as required by Rule 13 of the Energy Licence Modification Appeals: Competition and Markets Authority Rules (CMA70). Any revisions made to the timetable will be published on this website.
Date | Action |
---|---|
1 November 2021 | Publication of non-sensitive version of final determination and order |
30 October 2021 | Statutory deadline (with extension) for final determination |
28 October 2021 | Issue of final determinations to parties and interveners, and publication of summary |
Early September | Parties and interveners representations on provisional determination |
Week commencing 9 August 2021 | Issue of provisional determinations to parties and interveners, and publication of summary |
Late June/early July 2021 | Main hearings |
Mid-late May 2021 | Clarification hearings |
23 April 2021 | Deadline for GEMAs response and for any applications for permission to intervene |
31 March 2021 | Permission to appeal granted |
17 March 2021 | GEMA lodged submissions on whether permissions to appeal should be granted |
3 March 2021 | Permission to appeal sought by 9 parties |
CMA publishes final costs determination and order
23 June 2023: The CMA has announced its final determination on costs and costs order in relation to the Energy Licence Modification Appeals 2021:
- (23.6.23)
- (23.6.23)
- (23.6.23)
- (23.6.23)
The final determination on costs and the costs order were made on the basis of the parties to the appeal determined in October 2021. Since then, following the sale of the majority shareholding out of National Grid Group in January 2023, National Grid Gas plc has now been renamed National Gas Transmission plc.
CMA publishes final determination and order
1 November 2021: The CMA has published a non-sensitive version of its final determination (FD) and order in the Energy Licence Modification Appeals 2021 (issued on 28 October 2021). A second order was issued on 29 October 2021 under Rule 22 with corrections. The FD has been published in separate volumes for practical reasons information in volume 1 relates to all volumes of the FD and Order:
- (1.11.21)
- (1.11.21)
- (1.11.21)
- (1.11.21)
- (1.11.21)
- (1.11.21)
- (1.11.21)
CMA publishes summary of its final determination
28 October 2021: The CMA has published a summary of its final determination (FD) in the Energy Licence Modification Appeals 2021. The full FD will be issued to the parties and interveners. A non-sensitive version of the full FD will be published as soon as reasonably practicable.
- (28.10.21)
Summary of provisional determination
11 August 2021: The CMA has published a summary of its provisional determination (PD) in the Energy Licence Modification Appeals 2021. The full PD will be issued to the parties and interveners.
- (11.8.21)
Appellant withdraws sub-ground of appeal
26 May 2021: On 17 May 2021, the CMA granted permission to Northern Gas Networks Limited to withdraw sub-grounds 4A(i) and 4B of Ground 4 of its appeal.
- (26.5.21)
GEMA Response to appellants submissions on CMA PR19 final determination
17 May 2021: On 10 May 2021, the CMA received GEMAs Response to the appellants submissions on the CMAs Final Report on Ofwat Price Determinations.
- (17.5.21)
- (17.5.21)
Appellants Replies to GEMAs Response
17 May 2021: On 10 May 2021, the appellants replied to GEMAs Response to the appellants Notices of Appeal.
- (17.5.21)
- (17.5.21)