Detailed guide: Appeals: average time they take broken down by stage

Planning Inspectorate

February 17
10:41 2020

Planning (including listed building) appeals

These appeals will be in respect of a decision that the local planning authority (LPA) has made in relation to a planning application other than a householder appeal.

For appeals dealt with by written representations or a hearing:

Planning Appeal Receipt to Start Start to Event Event to Decision
Written Representations 7 weeks within which:
Receipt to Validation is 2 week
10 weeks 7 weeks
Hearings 13 weeks within which:
Receipt to Validation is 3 weeks
16 weeks 7 weeks

For appeals dealt with by an inquiry:

Planning appeals that are decided following an inquiry do not have a separate validation stage. Instead, when the appeal is started, the start letter declares the appeal to be valid, and the necessary validity checks will have been carried out so that an inquiry can arranged.

Planning Appeal Receipt to Start Start to Event Event to Decision
Inquiries 10 weeks 22 weeks 12 weeks
Planning Appeal Inquiry Rosewell Review Receipt to Start Start to Event Event to Decision
Inquiries 6 weeks 16 weeks 8 weeks

These are appeals relating to refusal for development associated with a house such as a rear extension or roof alteration, refusal to display an advertisement or sign and refusal for minor commercial development such as ground floor alterations like shop fronts and security shutters.

Householder Appeal Receipt to Start Start to Event Event to Decision
Written Representations 9 weeks within which:
Receipt to Validation is 1 week
6 weeks 4 weeks

All enforcement and lawful development certificate appeals

These are appeals against an enforcement notice (including listed building enforcement) or lawful development certificate in respect of your property.

Enforcement Appeal Receipt to Start Start to Event Event to Decision
Written Representations 16 weeks within which:
Receipt to Validation is 3 weeks
13 weeks 5 weeks
Hearings 48 weeks within which:
Receipt to Validation is 13 week
17 weeks 6 weeks
Inquiries 49 weeks within which:
Receipt to Validation is 5 weeks
23 weeks 6 weeks
Published 1 January 2014
Last updated 17 February 2020 +show all updates
  1. Data updated with January 2020 figures

  2. New figures added

  3. Average times updated

  4. Average timescales updated

  5. Average timescales updated

  6. Average timescales updated

  7. Average times updated

  8. Average times updated

  9. Average times updated

  10. average timescales updated

  11. average timescales updated

  12. Average timescales updated

  13. Data updated

  14. Data updated with new waiting times

  15. average timescales updated

  16. Updated times

  17. Average timescales updated

  18. Average figures updated

  19. First published.

Related Articles

Comments

  1. We don't have any comments for this article yet. Why not join in and start a discussion.

Write a Comment

Your name:
Your email:
Comments:

Post my comment

Recent Comments

Follow Us on Twitter

Share This


Enjoyed this? Why not share it with others if you've found it useful by using one of the tools below: