Response to Public Accounts Committee statement

Nuclear Decommissioning Authority

March 4
00:00 2015

National Audit Office: Progress on the Sellafield site an update, March 2015

The NDA continues to report openly about the challenges faced in tackling the historic legacy at Europes most complex and hazardous nuclear site.

The primary reason for increases in costs and schedule is because we now have a better understanding of the technical approach necessary to tackle these unique facilities that date back to the 1940s and 50s.

Nuclear provision: explaining the cost of cleaning up Britains nuclear legacy

NDA Annual Report and Accounts 2013 to 2014

Programmes and Major Projects Report: Sellafield

Before deciding whether to cancel the contract with Nuclear Management Partners the NDA needed to first satisfy itself and Government that it had an alternative model that would give greater confidence of delivering progress and value for money. We have been through a thorough process to underpin that important decision.

New Management Arrangements for Sellafield: Stakeholder Briefing

We look forward to having the opportunity to expand on these points at the Public Account Committee session on 11 March 2015.

Related Articles

Comments

  1. We don't have any comments for this article yet. Why not join in and start a discussion.

Write a Comment

Your name:
Your email:
Comments:

Post my comment

Recent Comments

Follow Us on Twitter

Share This


Enjoyed this? Why not share it with others if you've found it useful by using one of the tools below: